Update on ILEAS Training Center Remodeling Project

Update - November 8, 2023 

  • We reported before that the anticipated time for the parking lot expansion and repaving would not occur until spring of 2024.  Fortunately, Open Road Paving got right to it and will be largely done by November 10th.  There are now a total of 151 parking spaces at the Training Center.  check out the photos during and after their work.  
  • The demolition is well underway in the B Wing.  The contractors have removed the walls from approximately about 15 offices and other spaces.  One part of the wing will be converted into a classroom and the other will be used as an open area for tactical training. The next step is to start refinishing the area into usable space.  
  • As of November 10th, the asbestos removal project will be completed.  
Parking Lot B Wing
Parking Lot Before and After In-Progress B Wing

 

UPDATE - September 22, 2023

  • After receiving sealed bids, Felmley Dickerson Company of Champaign, Illinois was selected as the general contractor for this project.  
  • The asbestos removal contractor that started on August 21st, has cleared asbestos from the B Wing and the Basement Communications Storage area.  They are currently finishing up the C Wing.  It is anticipated that within two weeks, asbestos abatement for the entire building will be completed.    
  • Felmly Dickerson has begun the demolition work in the B Wing and the center courtyard. 
  • Bids were let for the replacement of the current parking lot and its expansion to the west.  
    • Open Roads paving submitted the only bid. 
    • Contract negotiations are underway with Open Roads Paving to begin work (most likely to begin in early Spring of 2024).

ILEAS would also like to thank the late Senator Scott Bennett and his family for working hard to identify the funding to make this project come to life.  

 

UPDATE - August 1, 2023

  • IGW Architects from Urbana, Illinois was selected as the architect and project manager. 
  • Reliable Environmental Solutions, Inc. from Springfield, Illinois was selected as the asbestos abatement project manager. 
  • After receiving sealed bids, Felmley Dickerson Company of Champaign, Illinois was selected as the general contractor for this project.  
  • Bidding is underway to select an asbestos abatement contractor.  
    • Asbestos abatement starts on August 21st.
    • Once that is complete, then the general contractor will start its remodeling work.  
  • The ILEAS Governing Board has met and approved the plan and the expenditure of the funds and engagement of contracts 
  • Over the summer, ILEAS part time individuals who were assigned some demolition work (removal of cabinets, cleaning, furniture/equipment moving) to prepare the A and B Wings for construction. 
  • Berns, Clancy and Associates of Urbana, Illinois was selected as the parking lot engineers. 
    • Bidding will begin shortly for the parking lot contractor.  

It should be noted that the State of Illinois Department of Commerce and Economic Opportunity (DCEO) developed Business Enterprise Program (BEP) goals for this project. The BEP goals established by DCEO was the hiring of minority and female-owned businesses.  The goals were set at 11% minority-owned businesses/contractors and 7% female-owned businesses/contractors. with regard to the general and asbestos contractors, ILEAS has met those goals.   

ILEAS would also like to thank the late Senator Scott Bennett and his family for working hard to identify the funding to make this project come to life.  

________________________________________________________________________

As we have previously announced, ILEAS received a $3 million grant from the State of Illinois through the Department of Commerce and Economic Opportunity (DCEO) to remodel the ILEAS Training Center (ITC).  The grant is routed from through the City of Urbana to ILEAS as a sub-grantee.  ILEAS is currently awaiting the final approval from DCEO.  However, we have already issued an RFP for architectural services and selected IGW Architecture (IGW) from Urbana as the project architect.  The project budget will be $2.975 million ($25,000 retained by Urbana for grant processing).  Based on a previous feasibility study, the remodeling will focus on:

  • Remodeling and upgrading the basement storage area in order to safely store and secure communications technology
  • Expand and resurface the north parking lot to accommodate more vehicles
  • Demolish individual rooms and remove the ceiling in the B Wing of the building in order to accommodate more versatile scenario-based training events 
  • Remove the remaining asbestos in the building 
  • Expand the shipping/receiving area 
  • Create a new "laboratory" style classroom where training can be conducted that requires the ability to be cleaned easily.  This includes the annual EOD robot maintenance training, crime scene processing and other training that cannot be conducted in a normal carpeted classroom 
  • Clean-up of one of the five enclosed courtyards to be used for outdoor training not visible to the public

Bids for the work have been going out and the engineering/architectural work is being completed. Once the remodeling is completed, ILEAS will have a community-wide open house to highlight what is available at the ITC for professional groups to rent/lease.  

As we have previously announced, ILEAS received a $3 million grant from the State of Illinois through the Department of Commerce and Economic Opportunity (DCEO) to remodel the ILEAS Training Center (ITC).  The grant is routed from through the City of Urbana to ILEAS as a sub-grantee.  ILEAS is currently awaiting the final approval from DCEO.  However, we have already issued an RFP for architectural services and selected IGW Architecture (IGW) from Urbana as the project architect.  The project budget will be $2.975 million ($25,000 retained by Urbana for grant processing).  Based on a previous feasibility study, the remodeling will focus on:

  • Remodeling and upgrading the basement storage area in order to safely store and secure communications technology
  • Expand and resurface the north parking lot to accommodate more vehicles
  • Demolish individual rooms and remove the ceiling in the B Wing of the building in order to accommodate more versatile scenario-based training events 
  • Remove the remaining asbestos in the building 
  • Expand the shipping/receiving area 
  • Create a new "laboratory" style classroom where training can be conducted that requires the ability to be cleaned easily.  This includes the annual EOD robot maintenance training, crime scene processing and other training that cannot be conducted in a normal carpeted classroom 
  • Clean-up of one of the five enclosed courtyards to be used for outdoor training not visible to the public

Bids for the work have been going out and the engineering/architectural work is being completed. Once the remodeling is completed, ILEAS will have a community-wide open house to highlight what is available at the ITC for professional groups to rent/lease.